Route 5 North between Santiago and the El Melón tunnel: a US$456 million project adds lanes and Free Flow tolls

· By , journalist

Route 5 North between Santiago and the El Melón tunnel: a US$456 million project adds lanes and Free Flow tolls

VíasChile, a subsidiary of Abertis, submitted to Chile's Environmental Assessment Service the environmental impact study for works on Route 5 North between Santiago's northern exit and the southern access to the El Melón tunnel: an investment of about US$456 million over more than 116 kilometres, [La Tercera](https://www.latercera.com/pulso/noticia/viaschile-comienza-la-tramitacion-ambiental-de-las-nuevas-obras-para-la-ruta-5-santiagolos-vilos/) reported on 23 November 2026. The project adds a fourth lane in each direction leaving Santiago, third lanes up to Nogales and barrier-free toll collection (Free Flow).

It is the first stage of the second concession of Route 5 Santiago-Los Vilos, awarded in August 2024, with a total estimated investment of more than US$1.2 billion. Construction would begin in March 2029 and finish in the first half of 2033, according to the Ministry of Public Works schedule cited by CNN Chile. For anyone driving to La Serena, Los Vilos or the Norte Chico this summer, the road stays as it is.

The Route 5 North project in figures
US$456.2 MInvestment
116KilometresSantiago - El Melón tunnel
4Lanes each way leaving Santiago3 today; works from March 2029
1,150Peak workforce
View the data as a table
InvestmentUS$456.2 M
Kilometres116
Lanes each way leaving Santiago4
Peak workforce1,150

What works the Route 5 North project includes

SectionDistrictsTodayWith the project
Buenaventura interchange – Batuco-Liray interchange (10.7 km)Quilicura, Lampa and Colina3 lanes each way4 lanes each way
Batuco-Liray – El Melón tunnel south access (about 102 km)Lampa, Tiltil, Llay-Llay, Hijuelas, La Calera and Nogales2 lanes each way3 lanes each way
Las Chilcas slopeBetween Tiltil and Llay-LlayAlignment modified a few years agoNo changes (80 km/h)
TollsWhole sectionToll plazas with barriersFree Flow electronic tolling, phased in
Service roadsLampa, Tiltil, Llay-Llay, Hijuelas, La Calera and NogalesExistingNew and repaved

Sources: La Tercera, CNN Chile and Meganoticias, with data from the environmental impact study filed with the SEA. Design speed would be 120 km/h, with sections at 100 km/h and the Las Chilcas slope at 80 km/h.

Kilometres of Route 5 North gaining one lane each way
View the data as a table
3 to 4 lanes10.7 km · Buenaventura - Batuco-Liray
2 to 3 lanes102.0 km · Batuco-Liray - El Melón tunnel, except Las Chilcas
Cars approaching the northern access of the El Melón tunnel on Route 5 North
The northern access of the El Melón tunnel, in Nogales, where the project section ends. Photo: Sfs90 (CC BY-SA 4.0), Wikimedia Commons.

When the Route 5 North works would be finished

The timeline is long. The study is only now entering review, and the company itself estimates three years and eight months of construction. This means there will be no changes to the road from this project this summer or in the next two.

Timeline of Route 5 Santiago-Los Vilos, Santiago-El Melón section
  1. Aug 2024Concession awarded
  2. Nov 2026Environmental impact study filed
  3. Mar 2029Estimated start of works
  4. H1 2033Full opening
MilestoneDateSource
Award of the Route 5 Santiago-Los Vilos concessionAugust 2024La Tercera
Filing of the environmental impact study for the Santiago-El Melón sectionNovember 2026La Tercera
Estimated start of worksMarch 2029Ministry of Public Works, via CNN Chile
Full openingFirst half of 2033Ministry of Public Works, via CNN Chile and Meganoticias

The company estimates an average of 450 workers during construction and up to 1,150 at peak, according to the study cited by La Tercera. Once operating, the section would employ between 25 and 75 people.

What Route 5 North means for travellers this summer

  • No immediate changes. Works do not start before 2029: the section keeps its current lanes and tolls through the 2026-2027 summer.
  • Free Flow in the future. Barrier-free tolling would gradually replace today's toll plazas. No rates have been published for that system yet.
  • The Las Chilcas slope stays the same. It is one of the slowest points for trucks and buses; the project keeps its alignment and its 80 km/h limit.
  • Plan around long weekends. Santiago's northern exit gets congested on public holidays. Check Chile's 2027 holidays and leave early.
Northern mouth of the El Melón tunnel with cars heading onto Route 5 North
Northern mouth of the El Melón tunnel, on Route 5 North. Photo: Sfs90 (CC BY-SA 4.0), Wikimedia Commons.

Destinations reached by Route 5 North

This section is Santiago's gateway to the northern Valparaíso coast, Los Vilos, La Serena and the north. If you are driving this summer, these guides will help:

Frequently asked questions

How much does the Route 5 North project cost?

About US$456 million for the section of more than 116 km between Santiago's northern exit and the El Melón tunnel. The full Santiago-Los Vilos concession exceeds US$1.2 billion.

When do the works start?

In March 2029, according to the Ministry of Public Works schedule, provided the environmental review keeps to plan. Completion is projected for the first half of 2033.

Will toll barriers disappear?

The project proposes gradually replacing them with a Free Flow electronic toll system. Rates and the timeline for that change have not been published.