Chile's Public Works Ministry (MOP) has pledged to finish by December 2029 the Vicuña-Yendegaia road, the 139.6 km route that crosses southern Tierra del Fuego to the Beagle Channel and that, with a barge crossing, will bring Puerto Williams closer to the rest of Magallanes. 28.1 km remain, Radio Polar reported on 13 November, after work began on stage 12 at Caleta 2 de Mayo, inside Yendegaia National Park.
Deputy Public Works Minister Nicolás Balmaceda announced investment of about CLP 80 billion to speed up the works, according to Emol. The new deadline is about a year and a half earlier than the original one. Work began in 1994 and is carried out by the Army's Military Work Corps (CMT).
The Vicuña-Yendegaia road in figures
View the data as a table
| Total km | 139.6 |
| Km still to build | 28.1 |
| Announced investment | $80 bn |
| Completion year | 2,029 |
| Item | Value | Source |
|---|---|---|
| Total length | 139.6 km in 14 stages, from the Rasmussen river to Yendegaia bay (plus a 13 km branch to Caleta María) | Radio Polar |
| Km remaining | 28.1 km | Radio Polar |
| Km built | About 111.5 km (Viajando Chile calculation from the figures above) | Radio Polar |
| Announced investment | About CLP 80 billion | Emol |
| Works started | 1994 | Radio Polar |
| Pledged deadline | December 2029 | Deputy Minister Balmaceda, via Radio Polar and Emol |
| Highest point | About 850 m, crossing the Darwin range | Emol |
What the trip to Puerto Williams will be like on the Vicuña-Yendegaia road
The link will be two-mode: you drive to Caleta 2 de Mayo, on the shore of the Beagle Channel, and from there take a sea crossing of about two hours to Puerto Navarino, on Navarino Island, close to Puerto Williams. According to Radio Polar, this would cut about 12 hours from today's sea connections, which take more than 30 hours. Emol describes the full trip from Punta Arenas with two barge crossings: one over the Strait of Magellan to Tierra del Fuego and one over the Beagle.
Today Puerto Williams is reached by plane from Punta Arenas or on the ferry through the channels. We explain it in our Puerto Williams and Navarino Island guide.

Why the Vicuña-Yendegaia road is taking so long
The 28 km still to build include crossing the Darwin range, in total isolation, with temperatures down to -15 °C, strong winds and areas flooded by beaver dams, Emol details. To speed things up, the MOP added civilian and military staff, more machinery and 20-days-on, 20-days-off shifts that keep work going all year, with two daily shifts in summer, Lieutenant Colonel Rodrigo Vergara of the CMT told Radio Polar.
- 1994Works begin
- Nov 2026Stage 12 begins at Caleta 2 de Mayo28.1 km remain, including the crossing of the Darwin range.
- Dec 2029Final connection pledged by the MOP
Yendegaia National Park, the destination at the end of the road
The road ends inside Yendegaia National Park, 150,612 hectares made up of 38,750 hectares donated by Douglas Tompkins and 111,832 hectares of state land, managed by Conaf, according to Wikipedia. It borders Argentina's Tierra del Fuego National Park and has Magellanic coihue and lenga forests, guanacos and Yagán shell middens on the coast. Today it gets almost no visitors because access is so hard: the road could change that. For scale, see Chile's largest national parks.

What officials said
- Nicolás Balmaceda, deputy public works minister: "the start of a new stage that will deliver, by December 2029, our commitment as the Public Works Ministry".
- Ericka Farías, regional presidential delegate: "During this government we intend to connect the remaining sections and open this road in 2029".
- Rodolfo Moncada, provincial presidential delegate: "here we are not only building a road, we are building the future of Puerto Williams".
A May 2025 report spoke of finishing the road in 2031, so the new deadline is an acceleration that remains to be seen. Meanwhile, if you are heading to the end of the world this summer, see also the southernmost hotel, The Cormorant at 55 South, and what to do in Punta Arenas.
Frequently asked questions
When will the Vicuña-Yendegaia road be finished?
The MOP has pledged the final connection for December 2029.
How many kilometres remain?
28.1 km out of 139.6 km, according to Radio Polar (13 November 2026).
Will you be able to drive to Puerto Williams?
Not all the way: the last leg is a sea crossing of about two hours between Caleta 2 de Mayo and Puerto Navarino, on Navarino Island.
Can you visit Yendegaia National Park today?
Access is by sea and via the road under construction, with no regular tourist services. Before planning a visit, check with Conaf Magallanes.