Chile's Ministry of Public Works (MOP) has begun widening Route 41-CH, the road linking La Serena with the Elqui Valley and the Agua Negra pass, on a first stretch of more than four kilometres within La Serena, with an investment of over 29 billion pesos and a 900-day schedule, Diario El Día reported on Saturday 28 November. The work is being carried out by the Roads Directorate with public funds, so there will be no toll, and it should be finished by late 2028.
The news comes in a difficult month for the road. On 18 November, Mi Radio gathered three reports from drivers hit by falling rocks near the Puclaro reservoir, one with an injured passenger, and described potholes inside the Puclaro tunnel caused by water seepage. Higher up, in the high Andes, clearing the road to Agua Negra still has no date because of record snowfall and avalanches, according to the authorities' site visit on 27 November reported by Elqui Global.
The Route 41 widening in numbers
View the data as a table
| First section investment | $29 bn |
| Construction period | 900 days |
| Section length | +4 km |
| Tourists via Juntas del Toro in 2025 | 56,448 |
| Project detail | Value |
|---|---|
| Section | Panorámica/Colo Colo junction to Quebrada de Monardez (La Serena) |
| Length | Over 4 km |
| Investment | Over 29 billion pesos |
| Schedule | 900 calendar days from early November 2026 |
| Estimated completion | Late 2028 |
| Toll | No: public works, not a concession |
| Works | New lanes, structures, storm drains, traffic lights, lighting, landscaping and access to La Florida airport |
Source: MOP and regional Public Works secretary Cristian Smitmans, via Diario El Día (28 November 2026). In the first months, work will take place outside the existing carriageway, so no road closures have been announced. Smitmans asked drivers to "drive carefully and respect the signs", and the MOP said the Roads Directorate is still engineering the next section: this project is "a first step in a much bigger challenge". For now, it does not include a dual carriageway to Vicuña.
Rockfalls near Puclaro: what drivers reported
The most delicate stretch for tourists is between the Puclaro reservoir and Vicuña, where Route 41 runs hemmed in by hills. These are the cases published by Mi Radio; the outlet did not include a response from the MOP or any other authority:
- 31 OctoberRocks hit two cars near Puclaro
- Early NovemberWidening works begin in La Serena
- 15 NovemberA rock injures a passenger on the way to Pisco Elqui
- 18 NovemberPotholes reported in the Puclaro tunnel
- 27 NovemberOfficials inspect clearing towards Agua Negra: no date
- Late 2028Estimated completion of the first section
| Date | Place | What happened |
|---|---|---|
| 31 October, 7:45 pm | Puclaro reservoir, about 500 m before the tunnel | Rocks break the windscreen and damage the roof and rear of a family car; no injuries |
| 31 October, 8 pm | El Chape bridge, near the tunnel | A rock breaks the driver's window and cuts his face |
| 15 November, 7 pm | Road towards Pisco Elqui | A rock of about 25 x 30 cm falls on a pickup carrying five people; one passenger injured and treated in Vicuña |
| 18 November | Puclaro tunnel | Potholes 35-40 cm long and 15 cm deep caused by water seepage |
Source: Mi Radio (18 November 2026). Those affected called for preventive measures and warned that a nearby containment net looked worn. Until there is an official response, the practical advice is to avoid stopping below slopes, avoid driving that stretch at night if you can choose, and slow down inside the tunnel.

Route 41 to Agua Negra: clearing still has no date
On 27 November, presidential delegate Víctor Pino, governor Cristóbal Juliá, Vicuña mayor Mario Aros and the regional secretaries for the Economy and Public Works went up to the La Laguna reservoir area to inspect the clearing. According to Elqui Global, a landslide near Llano Las Liebres, at almost 4,000 metres, is blocking machinery, and the Roads Directorate estimates at least five days just to clear it. The directorate asked the geology service Sernageomin to survey risk zones. "I cannot commit to a date," Aros said; Smitmans added that the road will only open with "full guarantees".
The official target is January 2027, as we explained in our story on Agua Negra. What is at stake shows in the figures: 56,448 foreign tourists entered through the Juntas del Toro complex, Chile's control post for the pass, in 2025, the highest in the official series that begins in 2008.
| Year | Foreign tourists entering via Juntas del Toro |
|---|---|
| 2017 | 52.428 |
| 2018 | 42.535 |
| 2019 | 20.936 |
| 2020 | 11.331 |
| 2021 | 0 (closed) |
| 2022 | 6.325 |
| 2023 | 24.754 |
| 2024 | 30.034 |
| 2025 | 56.448 |
| 2026 (January-August) | 28.511 |
Source: Undersecretariat of Tourism and Sernatur, foreign tourist arrivals by border crossing (October 2026 release).
The pass depends on summer: of the 28,511 foreign tourists who entered through Juntas del Toro between January and August 2026, 17,862 did so in January, 63%. That is why every week of delay matters in Vicuña, Paihuano and La Serena, which receive the tourists from San Juan who cross by car. The regional economy secretary, Martín Argaluza, asked business groups to stay calm and said the pass will open as soon as it is technically safe, according to Elqui Global.
Distances on Route 41 and how to plan an Elqui trip
View the data as a table
| La Serena | Start of the widening |
| Puclaro reservoir | 56.6 km from La Serena; rockfalls |
| Vicuña | 62,7 km |
| Pisco Elqui | 100,9 km |
| Agua Negra pass | Closed; no date |
| Trip | Distance | Estimated time without traffic |
|---|---|---|
| La Serena - Embalse Puclaro | 56,6 km | 1 h 02 min |
| La Serena - Vicuña | 62,7 km | 1 h 05 min |
| Vicuña - Pisco Elqui | 39,0 km | 45 min |
| La Serena - Pisco Elqui | 100,9 km | 1 h 49 min |
| Vicuña - Agua Negra pass (border) | 160,5 km | 2 h 52 min |
Source: Viajando Chile calculation with the OSRM router on OpenStreetMap; times exclude roadworks, checks and stops. Vicuña has average highs of 27.8 °C in December and 28.8 °C in January and almost no rain, according to the 2016-2025 average from Open-Meteo: leave early and carry water. To plan the trip, see things to do in Vicuña and the Elqui Valley, the pisco route and things to do in La Serena and Coquimbo.
View the data as a table
| High | Low | |
|---|---|---|
| Jan | 28.8 °C | 17.9 °C |
| Feb | 29.2 °C | 18.5 °C |
| Mar | 28.1 °C | 17.9 °C |
| Apr | 25.4 °C | 15.7 °C |
| May | 23.0 °C | 13.4 °C |
| Jun | 20.5 °C | 9.9 °C |
| Jul | 20.6 °C | 10.1 °C |
| Aug | 21.6 °C | 10.9 °C |
| Sep | 23.0 °C | 12.3 °C |
| Oct | 24.7 °C | 14.0 °C |
| Nov | 26.5 °C | 15.4 °C |
| Dec | 27.8 °C | 16.6 °C |

- Avoid the peak return hours: El Día describes congestion at peak times and more cars in summer; Sunday afternoon is the worst time to drive back to La Serena.
- Follow roadworks detours: although work starts outside the carriageway, there will be machinery at the La Serena end until 2028.
- Do not drive into the high Andes: while Agua Negra is closed, the section above the La Laguna reservoir is not open to tourists.
- Check flood alerts: in November Senapred kept snowmelt alerts in the Elqui (see story).
Frequently asked questions
Are there closures on Route 41 because of the widening?
None have been announced: in the first months the work takes place outside the existing carriageway, according to the MOP. Still, drive carefully and follow the signs at the La Serena end.
When will the Agua Negra pass open?
There is no date. Authorities have ruled out December and are aiming for January 2027, depending on the weather and clearing of avalanches in the high Andes.
How long does it take from La Serena to Vicuña?
It is 62.7 km on Route 41, about 1 hour 5 minutes without traffic, according to our OSRM calculation.